The 50% Rule: Ineligible Costs
| Not all costs are eligible for inclusion in the 50% Rule. Although certain costs are not included in the 50% Rule calculation to determine whether the facility is eligible for replacement, the costs may be eligible for Public Assistance funding subject to all other eligibility requirements. | The numerator does not include costs associated with: | The denominator does not include costs associated with: |
---|
- Upgrades of non-damaged elements even if required by codes or standards (e.g., elevation of an entire facility triggered by repair)
- Demolition beyond that which is essential to repair the damaged elements
- Site work
- Soft costs
- Contents
- Hazard mitigation measures
- Emergency Work
| - Demolition
- Site work
- Soft costs
- Contents
- Hazard mitigation measures
- Emergency Work
|
|
|