Components of the Base Cost Estimate

The total estimated cost for each work activity is a product of quantity, unit price, and the city adjustment index/factor.

CEF Part A allows development of construction costs using a variety of FEMA-approved unit cost data sources. Local bids from recent projects of similar size and scope, industry cost-estimating references, or FEMA cost codes can be used for cost data sources.

Each requires validation of scope and cost reasonableness prior to using as the base cost estimate.

Select this link for a full description of Part A

CEF Part A. The item fields for Quantity, Unit Price, City Adj Factor, and Total Cost are highlighted. Please refer to Appendix 3-8 for a full description of CEF Part A.