Lesson 2 Overview and Objectives

This lesson provides an overview of FEMA's process for developing cost estimates.

At the end of this lesson, participants will be able to:

  • Describe the FEMA cost estimating process
Scenario: Replacing a Door (1 of 3)

How much do you think it would cost to replace this door?

  • What components of work are involved?
  • What factors impact cost?
An exterior door with multiple hazard signs, including danger of death.
Scenario: Replacing a Door (2 of 3)

If you research the cost of this project in RSMeans, the costs are approximately $1,360.00.

  • The customer might say, "Are you kidding? I found a door in Home Depot for $429."
  • The Applicant might say, "Every contractor I spoke to quoted $1,000."
CSINumberDescriptionQuantityUnitTotal Incl. O&P
08131 325 2990Doors, fire, "A" label, exterior, steel, commercial, flush, 1-3/4" x 7'-0" x 3'-6" wide Ea.$890.00
08121 313 0110Frames, steel, knock down, hollow metal, 16 gauge, up to 5-3/4" D, 7'-0" H, 3'-6" W single Ea.$247.00
08712 041 0011Door hardware, deadlocks, mortise, heavy duty Ea.$257.00
Scenario: Replacing a Door (3 of 3)

Costs involved in replacing the door include:

  • Removing the door
  • Hauling away the door
  • Renting a dumpster
  • Purchasing a new door and associated hardware
  • Installing the new door and hardware
  • Painting the door

Additional costs may apply in certain circumstances:

  • Hazardous site conditions or hazardous building materials
  • Restricted work area
  • Protection of building contents
  • Protection of public in the area
Cost Estimating Process

The primary steps in the estimating process were mentioned in the last lesson. They are:

  1. Identify Scope
  2. Develop Estimate
  3. Review
A person working at a computer in a large cubicle.
Scope of Work

The scope of work describes what is necessary to fix the facility. Defining the eligible scope of work is the most important aspect of the cost estimating process.

An accurate construction cost estimate begins with a well-defined, quantitative description of the project's scope of work. A poorly defined scope of work will cause inaccurate estimates.

FEMA works with the Applicant to develop the scope of work for eligible damages. This scope of work is also used to assist in preparing the cost of the grant.

A potential mitigation site on campus of Westmont College is inspected by FEMA and CalEMA public assistance staff led by Westmont staff in aftermath of the Tea Fire.
Elements of the Scope of Work

A scope of work includes:

  • All work items necessary to restore the facility to its pre-disaster design, function, and capacity in accordance with the laws, regulations, and policies that govern the Public Assistance program
  • Eligible upgrades necessary to meet current codes and standards, if applicable
  • Special Considerations
  • Incidental non-permanent work that is required as part of completing construction, (i.e. scaffolding, traffic control, temporary erosion control)
Inspection of building earthquake damage.
Scope of Work and Cost Estimating

The cost estimate is only as accurate as the information provided and the experience of the project formulation team. An accurate scope of work and appropriate unit cost data are required for an accurate estimate.

The costing specialist will review the scope of work information to ensure a full understanding of project conditions that may affect eligible costs.

A person working on a laptop and talking on a mobile phone in a cubicle.
Cost Data

There are four types of cost data. The difference among them is the level of detail in the scope of work and the unit costs used for each work element. The more detail provided, the more precise the estimate. A complete and detailed scope of work is essential for making an accurate cost estimate.

The Public Assistance program requires quantitative estimates, so only Detailed Data should be used.

  • Heuristic Data: Cost per highway lane-mile or cost per hospital bed. Early project stages, cannot be used to prepare large project estimates for the Public Assistance program

 

  • Parametric Data: Cost per square or cubic foot. Conceptual design phase, used for preliminary budgets or to check later estimates

 

  • Conceptual Data: Cost per square foot for assembled systems or major components. Bundles a series of construction components, best used as a budgetary tool in the planning stages of a project

 

  • Detailed Data: Cost of labor, material, and equipment to install one unit of a specific item of work. Scope of work must be well-defined, and all decisions regarding the facility's materials and methods should already have been made. Preferred estimating method in the Public Assistance program
Unit Cost Data

The focus of this lesson is on estimates developed using detailed unit cost data. Regardless of the source, the cost elements (i.e., labor, equipment, materials, overhead, and profit) that generates the unit cost data, it must be documented and understood so that the unit cost can be properly applied.

The unit cost data must also be reproducible by future users and reviewers of the estimate, such as FEMA project closeout staff or auditors.

Disaster supplies are piled high at the Journey Disaster Relief Center in Norman.
Cost Data Sources

There are three potential sources for cost data:

  • Local Historical Costs
  • Industry Costs-Estimating Software
  • FEMA Cost Codes
Rising and falling points on a graph above a dollar bill.
Local Historical Costs

Local historical costs are the preferred and most reliable source of cost data. To be used, costs must be similar to those being estimated, recent, and procured in compliance with Federal, State, and local procurement regulations by either the Applicant or other agencies in the same or nearby jurisdiction.

Historical contract costs must have been competitively awarded and in compliance with all relevant government regulations. The scope of work in contract prices should be similar to repair or restoration work. Data must include a schedule of values or unit rates applicable to the eligible work being (or to be) performed.

State Departments of Transportation are a frequent source of historical project unit cost data. Additionally, Department of Transportation projects frequently involve Federal funding, an indication that procurement policies are in compliance with Federal procurement requirements.

A person in a safety vest working on the roof of a building.
Calculating Local Historical Costs

Local historical costs must meet the requirements for producing a quantitative estimate. Data must also be accessible by others for verification and future use of the estimate.

When similar data are provided, it is recommended that the reported average of three low bids be used as a reasonable estimate of cost. In some cases, the contracted unit cost is higher than the average unit cost of the three low bids, suggesting the successful bidder used an unbalanced approach to prepare the bid.

The use of the average of three low bids will compensate for unreasonable unit costs, either high or low, used by the successful bidder.

A person sitting at a desk in front of a computer, analyzing financial data.
Construction Industry Cost-Estimating Software

Published industry standard construction cost-estimating resources include Xactimate, RSMeans, BNi Cost Books, Marshall & Swift, and Sweet's Unit Cost Guide. Unit cost data or estimating software used by the insurance industry is not approved for use in the Public Assistance program.

Unit cost data from published national construction cost databases must meet the same criteria as other unit cost sources. They must also:

  • Be specifically designed for the construction industry and recognized as credible
  • Provide documentation of the elements included in the unit costs (i.e., labor, material, equipment, overhead, and profit)
  • Document the assumptions included in the unit costs, e.g., union vs. non-union, labor, productivity
  • Be adaptable to project localities
A debris basin at Pickins yard is cleaned after severe winter weather caused flooding and landslides to fill the bowl.
RSMeans

RSMeans maintains a national construction cost database that provides accurate and up-to-date cost information that helps owners, developers, architects, engineers, contractors, and others to carefully and precisely project and control the cost of both new building construction and renovation projects. RSMeans' online database is called RSMeans On-Line.

RSMeans is widely accepted throughout the engineering and construction community and is generally consistent with other sources of construction cost data.

RSMeans CostWorks and 2011 Square Foot Costs
FEMA Cost Codes

FEMA cost codes are issued by the FEMA Regional Office. They are issued for a specific location or declaration.

Generally, FEMA cost codes represent complete installed costs and include:

  • Equipment
  • Materials
  • Labor
  • Direct construction costs
  • Supporting activities
  • Project support and management
  • Contractor profit

Some cost code data may be several years old and require escalation. FEMA cost codes are last on the list of acceptable cost data sources. Local historical costs or industry cost-estimating software should be used if possible.

Construction equipment at work rebuilding the approach to a bridge and lock of the New York State canal system that was destroyed by flooding from Hurricane Irene.
Construction Specifications Institute MasterFormat

The Construction Specifications Institute MasterFormat is an industry standard for organizing specifications and other written information for commercial and institutional buildings. The purpose of this format is to help the user locate specific types of information.

MasterFormat is a standardized list of numbers and titles for organizing construction documents, including cost estimates, by work results. A list of the 50 divisions is on the following slide.

MasterFormat provides a master list of divisions and section numbers and titles within each division to follow when organizing information about a facility's construction requirements and associated activities.

The Cost Estimating Format is designed to use the Construction Specifications Institute MasterFormat and to facilitate preparation of estimates using the Construction Specifications Institute (CSI) numbering system.

Clean-up and construction continue after an EF-5 tornado destroyed a third of Joplin, MO.
Construction Specifications Institute MasterFormat Divisions

Division 00: Procurement & Contracting Requirements

Division 01: General Requirements

Division 02: Existing Conditions

Division 03: Concrete

Division 04: Masonry

Division 05: Metals

Division 06: Woods, Plastics and Composites

Division 07: Thermal & Moisture Protection

Division 08: Openings (Doors & Windows)

Division 09: Finishes

Division 10: Specialties

Division 11: Equipment

Division 12: Furnishings

Division 13: Special Construction

Division 14: Conveying Systems

Division 21: Fire Suppression

Division 22: Plumbing

Division 23: Heating, Ventilation, and Air Conditioning

Division 25: Integrated Automation

Division 26: Electrical

Division 27: Communications

Division 28: Electronic Safety & Security

Division 31: Earthwork

Division 32: Exterior Improvements

Division 33: Utilities

Division 34: Transportation

Division 35: Waterway & Marine Construction

Division 40: Process Interconnections

Division 41: Material Processing and Handling Equipment

Division 42: Process Heading, Cooling, and Drying

Division 43: Process Gas and Liquid Handling, Purification and Storage Equipment

Division 44: Pollution & Waste Control Equipment

Division 45: Industry-Specific Manufacturing Equipment

Division 46: Water & Wastewater Equipment

Division 48: Electrical Power Generation

Advantages of Construction Specifications Institute MasterFormat

Construction Specifications Institute MasterFormat organizes all materials used in a construction project in a consistent format, which reduces errors. This provides a number of advantages:

  • Design teams know where their components fit into the final contract documents package
  • Contractors can separate construction documents by discipline and provide sections to trade subcontractors for bidding
  • Estimating Specialists can readily identify all related work associated with each discipline
Two people reviewing project plans and maps.
Applying Cost Estimates

The total estimated cost for each work activity is a product of quantity, unit price, and a city adjustment factor. These elements are assembled and calculated in the Cost Estimating Format.

View of pallets in a warehouse through a partially-open loading door. A National Guard officer is speaking to a truck driver in the foreground.
FEMA Validation of Cost Estimates

After cost estimates have been made, they must be reviewed and validated by FEMA. Applicants must submit relevant documentation for substantiating costs.

The FEMA review will focus on:

  • Eligibility
  • Reasonableness
  • Cost inflation factors

FEMA must also validate all competitively procured contracts. A third-party expert panel review is required for estimates with a federal cost share of $5 million or greater.

View of FEMA personnel working at a computer over project plans.
Cost Eligibility (1 of 2)

Eligibility is an essential factor in developing cost estimates. The Applicant, facility, and work must be eligible for a cost to be eligible for Public Assistance reimbursement. Ineligible costs should not be included in the Public Assistance estimate.

Eligible costs must:

  • Directly tie to the performance of eligible work
  • Be reasonable and necessary to accomplish the work
  • Comply with Federal, State, and local requirements for competitive procurement
  • Not be a duplication of benefits
  • Be traceable to one of three types of cost data: local historical costs, published industry costs, or FEMA cost codes
Construction workers steadying prefabricated stairs as a crane lowers them into place.
Cost Eligibility (2 of 2)

The final grant amount will be based on the cost estimate and programmatic adjustments including:

  • Insurance proceeds
  • No duplication of benefits
  • Salvage value
  • Other adjustments
A construction crew works in the fog to repair and rebuild the Avon by the Sea boardwalk after it sustained damage following Hurricane Sandy.
Cost Reasonableness

A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person under the circumstances prevailing at the time the Applicant makes the decision to incur the cost.

FEMA determines reasonableness by evaluating:

  • The cost is of a type generally recognized as ordinary and necessary for the type of facility or work
  • The cost is comparable to the current market price for similar goods or services based on:
    • Historical documentation
    • Average costs in the area
    • Published unit costs from national cost estimating databases
A skid loader offloading a trailer truck.
Cost Inflations Factors (1 of 2)

There are a variety of factors that may inflate costs involved with disaster response and recovery. FEMA evaluates the length of time the factors applied compared to the length of time costs were incurred.

  • Shortages in equipment, materials, supplies, labor, or contractors
  • Project-specific complexities, such as environmental or historic issues, remote access or location, provision of a unique service with few providers, or elements requiring an extraordinary level of effort
  • Exigent circumstances
A construction crew working with sections of large pipe while a crocodile lies nearby.
Cost Inflation Factors (2 of 2)

The Applicant is responsible for providing documentation to demonstrate its claimed costs are reasonable. If FEMA determines any of the costs to be unreasonable based on its evaluation, FEMA may disallow all or part of those costs.

As an example, a historic property needs to be re-built to historic standards, thus more expensive building materials and more custom labor are needed. Consequently, the Estimating Specialist must incorporate these elements and associated costs into the estimate.

Repairs to the historic New Jersey Transit Terminal after Hurricane Sandy in 2012.
Third-Party Expert Panel Review

A FEMA licensed engineer/architect with cost-estimating expertise or a certified cost estimator reviews all requests for replacement and validates the estimates. For any replacement requests over $5 million, the United States Army Corp of Engineers Center for Excellence for Cost Engineering performs an additional review of the repair and replacement estimates. FEMA considers the results of the USACE review prior to approving replacement.

For an Alternative Procedures Project with an estimated Federal share of at least $5 million, upon the Applicant's request, FEMA provides a FEMA-funded, independent validation of the cost estimate.

A contractor signing paperwork.
Lesson 2 Summary

This lesson provided an overview of FEMA's process for developing cost estimates.

The next lesson provides a detailed overview of the Cost Estimating Format tool.