Conducting Risk Assessment: Calculate Risk

The last step for conducting a Risk Assessment is calculating risk. Risk is the Impact rating multiplied by Probability rating, with the resulting number as your Risk. Let’s say you live near a river and have experienced flooding in the past. You rated the Impact at 3 and the Probability at 5 so your Risk would be 15 (3 x 5 = 15). Go through your hazard list and multiply the Impact rating by the Probability rating. When you’re done make a list of your hazards using your Risk number to rank them high to low.

Click here to access the Preparedness for Child Care Providers Toolkit.

 

This visual represents how to calculate risk. Hazard Impact multiplied by Hazard Probability equals Hazard Risk