Operational generator servicing requirements
| - If the generator is installed by USACE, the USACE contractor is responsible for performing all service requirements. The facility POC does not have to assume this requirement.
- Again, the generator will need to be shut off for these service items to occur. This may cause an inconvenience to facility operations, but these service requirements must be followed to ensure long term operational capability of the generator. And once again, this will require the facility to execute their electrical system “cold start” procedures after the service has been completed and the generator is ready to become operational again.