What happens when the lights go out?
| - Depending upon the type of facility you may own or operate, there may possibly be a statutory or perhaps an applicable “industry standard” that requires you to have a backup generator installed.
- If your facility supports governmental or community post-event first responder activities, there may be a statutory requirement for your facility to have backup power.
- In some other locations, facilities such as fueling stations along an evacuation route may be statutorily required to have backup electrical power available. Depending upon those statutory requirements or “industry standards” the generator might provide power to all, or to only a certain component, of the total electrical requirement of the facility.
- Some of those requirements may also dictate the installation of an automatic transfer switch to change the electrical feed into the facility from the commercial electrical distribution system, a.k.a “the grid”, to an electrical feed provided by the backup generator.
- Automatic Transfer Switches are not very common and are typically found in facilities where critical facility systems must remain in a non-interruptible operational condition such as in certain segments of hospitals, data processing centers, etc.
Audio Transcript |
|
Full Load Operational Tests
| - If your facility requires a generator, and one is in fact already installed, there are additional operations and maintenance activities that should be performed.
- Periodically scheduled full load operational tests should be part of your normal operations and maintenance routine for the generator and your facility.
- Many generator owners run only the generator engine on a frequent basis and the generator is rarely, if ever, operated under a full electrical load condition. As a result, the full suite of components found on the generator are not all “exercised” regularly.
- In many of those cases, many times after “the grid” has been impacted by an event, those generators typically operate for up to 48-72 hours before a component fails and they are no longer operational.
Audio Transcript |
|
Full Load Operational Exercise
| - Conducting full load operational exercises with the generator also assists with the development and exercising of facility electrical cold start procedures.
- Electrical equipment is prone to electrical power surge induced failure. Lightning strike at a facility can cause this, but surges caused by when the electrical power fails and comes back on unevenly or irregularly will also cause electrical equipment casualties.
- When a generator starts up, it takes a period of time until the electrical power it is producing “settles down” and is consistent. If electrical equipment is not temporarily isolated from the reenergizing of the facilities electrical system, it could damage some of that equipment.
Audio Transcript |
|
Questions to Ask (Continued)
| - If there is no statutory or other standard(s) that requires your facility to have a permanently installed backup power generator, there are still questions to be asked and answered.
- What services does your facility provide?
- How long can your business, your community, or your agency “survive” if those services are not available to you or the citizens?
- If the estimated date for commercial power grid restoration is estimated to be several weeks away, what then?
- This is the common situation most facility owners face after some disaster event has impacted the availability of electric power at their facility, be it some governmental agency owned “public” facility, or a privately owned facility or business.
Audio Transcript |
|
Manual Transfer Switches (1 of 3)
| - A manual transfer switch can simplify the installation process immensely.
- It allows the generator to be placed fairly close to the facility, minimizing the amount of electrical cabling required to connect the facility to the generator.
- If a manual transfer switch is not present, typically the electrical cables have to be run for a greater length to connect the generator to a facility’s interior electrical panel.
Audio Transcript |
|
Manual Transfer Switches (2 of 3)
| - When the transfer switch is switched to feed the facility’s electrical system from the generator, it will also disconnect the facility from the commercial power grid feed.
- This ensures no electricity from the generator back feeds to the power grid endangering the lives of the line worker working to restore the damaged electrical distribution system.
- This also protects the facility from any power surges from the commercial power grid as it is returned to operational status and re-energized.
Audio Transcript |
|
Manual Transfer Switches (3 of 3)
| - If a manual transfer switch is not in place, the fusible links must be physically disconnected to isolate the facility from the commercial power grid so electricity will not backfeed to the electrical grid from the generator.
- The personnel installing the generator may not have the correct tools or equipment to remove these fuses.
- This could require utility company support to accomplish. They may not be readily able to support your need in a timely fashion as they are working to reestablish the overall electrical distribution system as rapidly as they can.
- There are costs associated with installing a manual transfer switch, but the costs are significantly less expensive as compared to the costs of installing a generator. Keep in mind, manual transfer switches do not have the same operations and maintenance requirements as a generator.
Audio Transcript |
|
Water and Wastewater Sector